Power House Construction works

Road Maintenance and clearing at kharbari

Support piers renforcement work at sikteltaar

Formwork removal is in progress for the base slab of the intake structure

Installation of Primary intake gate has been ongoing

M25 concrete work is currently in progress on the base slab in front of the main intake
The MS embedded plate is being installed in the intake orifice.

M25 concrete work is in progress for the base slab of the intake structure


Support pier


Gravel flush under construction 70% done

Desander Basin construction







Installation of Construction Power Transformer 150KVA and accessories with Ariel Bundled Cable at Site

Site Clearance and Excavation Works at Peaking Reservoir

Installing RC pipe as Canal at site and road maintenance

Hydro Mechanical Works Steel Gates Construction works at Workshop

Hydro Mechanical Works Stoplog Gates Construction works at Workshop

Crusher Plant at Site





EXCAVATION WORKS AT PEAKING RESERVOIR SITE

CRUSHER PLANT AT SITE

AGGREGATE STOCK

MATERIAL STOCK FOR CRUSHER PLANT

FUELS STOCK FOR MACHINERY AT SITE


 Users Today : 9
 Users Today : 9 Users  Last 7 days : 70
 Users  Last 7 days : 70 Users Last 30 days : 251
 Users Last 30 days : 251 Users This Month : 251
 Users This Month : 251 Users This Year : 3370
 Users This Year : 3370 Total Users : 8192
 Total Users : 8192 Views Yesterday : 28
 Views Yesterday : 28 Views Last 7 days : 184
 Views Last 7 days : 184 Total views : 28189
 Total views : 28189