Nepal Electricity Authority (NEA) and SK Energy Pvt. Ltd. have signed a power purchase agreement for the Shyamkhola Hydropower Project (7.2 MW).
Detailed engineering design, drawing & report Completed.
Transmission line survey report,drawing and bid document is completed.
Bidding document for EM/HM/Civil Completed.
PPA approved from electricity Regulatory commision Collateral.
Performance Guarantee & Documents for PPA is completed.
Desk Study Report.
Survey License Obtained.
Feasibility Status Report (FSR).
Energy lock with (NEA).
IEE TOR Submitted to (DOED).
Grid connection Aggrement on 2078/09/20.
Land Purchase 99% complete.
Transmission Line Desk Study Report Done.
Transmission Line Survey License obtained.
IIE TOR Approved by DOED.
(NEW) Survey Licence Renewed.
Electromechanical MS FLAT Earthing below ground level materials successfully dispatched at site.
Upfront equity raised for term loan disbursement
Access road has been maintained and improved.
Excavation works of peaking reservoir has been 52.65% completed.
Excavation works of peaking reservoir has been 100% completed
Hydro Mechanical Local works Pathibhara Construction Works Contractor Awarded.
Hydro Mechanical Local works Pathibhara Construction Works Contractor dispatched the Rolling Machine Steel gates Stop Log and other material dispatched at the project site and Saddle plate has been manufactured at site and installing the materials.
Hydro Mechanical Pipe Fabrication and Expansion Joints Contract Awarded to HH Steel.
Hydro Mechanical Pipe Fabrication and Expansion Joints HHSteel Succesfully finished the production of pipes and joints and the material.

Users Today : 9